The Canada-based Norbord OSB-manufacturing company will be relocating an existing continuous press from its factory in Alberta / Canada to Inverness in Scotland where it will be incorporated into a new OSB line. The order for a new OSB drum dryer with the corresponding energy plant has been placed with Büttner.
The single-path drum dryer sized 6.5 x 36 R will have a throughput capacity for dry strands of 45 t/h. Besides the entire equipment for handling the air processes with steel construction and insulation, the scope of delivery will also include a 500 m³ wet-material horizontal metering bin.
The energy plant with a total combustion capacity of 55 MW will use a 75 m² grate to generate around 40 MW of flue gas for heating the dryers and 15 MW for heating thermal oil. As with the drum dryer, Büttner will also be supplying the entire range of equipment commencing with a moving floor for the fuel storage and continuing right up to the primary circulation system for thermal oil, which will include the piping, brick lining, steel construction and insulation.
The complete assembly of the dryer and energy plant is also included in Büttner's scope of delivery and is to be concluded by the middle of 2017.